Colleges and Universities
|
Strozier Library Renovations
Tallahassee, Florida

The work, spread out over multiple contracts and phases, included roofing, waterproofing, replacement of 2 elevators, and the demolition and renovation of the majority of the first floor of the Library. Working closely with FSU, we must maintain access to all other areas of the Library for the staff and students. Roofing and waterproofing will be completed by early October, and the renovations of the main floor will be completed in December. The elevators will be returned to service in February 2010.
Project Facts
| Project Size: |
32,500 sq.ft. |
| Finish Date: (est.) |
February 2010 |
Noteworthy Aspects
• Multiple Contracts/Phasing
• Occupied Building
• Elevator Replacement
• Roofing/Waterproofing
Architect
Lewis + Whitlock
Tallahassee, Florida 32303
(850) 942-1718
Rodney Lewis, AIA, Project Architect
|
|
|
|